AAO Lesson 100: Control price variation across payments and delays
AAO · Lesson 100 · English
Control price variation across payments and delays
Study time: about 145 minutes including practice. Prerequisites: AAO-099, AAO-080.
Learning outcomes
- Exclude already-paid price portions from later variations under the supplied dates.
- Distinguish supplier-default delay from a specific authorised delivery-date amendment.
- Reconcile selected tax/exchange and payment terms without double counting.
1. A correct index ratio is only part of a valid claim
Rule 225(viii)(f)–(k) adds payment, delay, tax, exchange and settlement controls to the formula developed in AAO099. A mathematically correct latest-index calculation can still use a price portion that has already been paid, a date disallowed for supplier default, or an element already adjusted elsewhere.
The selected baseline remains 19 June 2024. All dates, allocations, indices, rates and clause mechanics below are fictional teaching facts. No real price claim, payment, extension or liquidated-damages determination is made. The reconstructed weighted formula retains the source-display caveat explained in AAO099.
2. Freeze paid portions after their payment dates
Clause (f) requires a stipulation that price variations are not admissible on the relevant portions after the dates of advance or stage payments. Identify both the portion and the date. Do not treat a payment as if it froze the entire contract, or ignore it and vary the full price again.
In an original continuation of Cedar, base price is ₹2,000,000, with fixed/material/labour shares of 20/50/30. A ₹400,000 advance is paid on 1 September 2023. The supplied approved clause allocates that advance proportionately across the three price components. The stipulated indices had not changed at that payment date, so no earlier variation on that portion remains due. There are no other earlier payments.
The original scheduled delivery is 30 June 2024. At the agreed original input cutoffs, the supplied teaching material ratio is 210 ÷ 200 = 1.05 and the wage ratio 262.5 ÷ 250 = 1.05. Cedar retains the earlier stipulated gross upward trigger exceeding 2% of the entire base price and an upward ceiling of 6% of that base.
| Component | Base amount | Paid and frozen at the supplied base indices | Unpaid base | Calculated unpaid amount at original cutoffs |
|---|---|---|---|---|
| Fixed 20% | ₹400,000 | ₹80,000 | ₹320,000 | ₹320,000 unchanged |
| Material 50% | ₹1,000,000 | ₹200,000 | ₹800,000 | ₹800,000 × 1.05 = ₹840,000 |
| Labour 30% | ₹600,000 | ₹120,000 | ₹480,000 | ₹480,000 × 1.05 = ₹504,000 |
| Total | ₹2,000,000 | ₹400,000 | ₹1,600,000 | ₹1,664,000 |
The adjustment on the unpaid portion is ₹1,664,000 − ₹1,600,000 = ₹64,000. This is 3.2% of the entire ₹2,000,000 base, so it passes the supplied strict 2% trigger and is below the ₹120,000 ceiling. The total contractual price in this limited case becomes ₹2,064,000. After crediting the already paid ₹400,000, the remaining amount before any separately applicable deduction is ₹1,664,000.
Varying the full base at 4% would give ₹80,000, overstating this adjustment by ₹16,000. That excess is precisely the post-payment 4% variation wrongly applied to the paid ₹400,000. Adding the advance to ₹2,064,000 again would be a different error: double-counting a payment credit as new consideration.
The proportional allocation is an explicit contract assumption, not an automatic method prescribed for every advance. If the contract identifies a payment with particular deliverables or components, use that actual allocation and the relevant dates.
3. Distinguish the cause of delay and the actual amendment
Clause (h) bars variation beyond the original scheduled delivery date for defaults attributable to the supplier. Clause (i) permits variation beyond that date through its specific alteration by contract amendment in cases of force majeure or Government default. An event label alone is not the amendment.
| Scenario | Date/index evidence | Permitted calculation on the supplied facts | Result before separate deductions |
|---|---|---|---|
| A: delivery under original schedule | Original cutoffs give ratios 1.05 and 1.05 | Unpaid portion adjustment ₹64,000 | Price ₹2,064,000; less paid ₹400,000 leaves ₹1,664,000 |
| B: supplier-default delay; goods accepted 31 August 2024 | Later ratios are 1.10 and 1.10, but original schedule/input cutoffs are unchanged | Do not substitute the later ratios; retain the original ₹64,000 adjustment | Price remains ₹2,064,000 before the stipulated damages below |
| C: supplied qualifying force-majeure case with a properly authorised specific amendment | Amendment expressly changes scheduled delivery and relevant input cutoffs; supplied applicable ratios become 1.10 and 1.10 | Unpaid base ₹1,600,000 × 8% = ₹128,000 gross, limited to the stipulated ₹120,000 upward ceiling | Price ₹2,120,000; less paid ₹400,000 leaves ₹1,720,000 |
Scenario C expressly supplies the qualifying event, competent amendment and revised input dates. It does not establish that every event called force majeure automatically extends dates or permits a chosen index. If the file has only a contractor’s letter requesting more time, the amendment gate remains open. A revised delivery date also must not silently erase the material/labour cutoff conditions.
The higher-index calculation would be ₹128,000 before Cedar’s ceiling, but it is not payable in supplier-default scenario B. Do not use a correct arithmetic figure to bypass the date restriction. Conversely, apply an actually authorised relevant amendment on its own terms rather than treating every extension as supplier default.
4. Calculate percentage damages on the properly varied price
Under clause (g), where late deliveries are accepted subject to contractual liquidated damages and those damages are a percentage of price, that percentage applies to the price as varied by the clause. The source does not provide a universal percentage or cap; use the actual contract.
For scenario B only, the fictional contract and competent case decision supply liquidated damages of 1% of the whole properly varied price. No other deduction is assumed. The correct base is ₹2,064,000, so damages are ₹20,640.
| Step | Amount | Explanation |
|---|---|---|
| Base price | ₹2,000,000 | The original complete consideration |
| Admissible original-date variation | +₹64,000 | Paid portion excluded; prohibited later indices not used |
| Properly varied price | ₹2,064,000 | Base for the stipulated 1% damages |
| Stipulated damages | −₹20,640 | 1% × ₹2,064,000 |
| Less advance already paid | −₹400,000 | Payment credit, not another expense or price increase |
| Remaining amount in this limited bridge | ₹1,643,360 | Subject to other actual settlement requirements, not assumed authority to pay |
Using 1% of the unvaried ₹2,000,000 would produce ₹20,000, understating the stipulated damages by ₹640. Using the prohibited later-date price would create a different wrong base. Neither error is repaired by simply subtracting the advance earlier in the percentage calculation, because the supplied damages term uses the whole varied price.
5. Separate duties and foreign-exchange elements
Clause (j) requires the price’s stated duties/tax elements and the selling-rate foreign-exchange basis for relevant imported items, together with the calculation method and supporting documents for variations. Its legacy reference to excise wording is not evidence that a particular tax applies today. Actual law, applicability, rates and contract terms require verification.
Consider a separate original imported-equipment example with a stipulated twenty-four-month delivery period and an appropriately agreed price-variation clause satisfying the previously taught eligibility requirements. Its clause identifies a USD 10,000 foreign-currency element at a base selling rate of ₹82 per USD, a separately stated duty/tax component of ₹60,000, and an unchanged local component of ₹300,000. A verified teaching claim supplies an applicable selling rate of ₹84 and a revised duty/tax component of ₹54,000. These are stipulated figures, not current market quotations or statutory rates. The clause expressly avoids applying another material index to the same exchange-adjusted element.
| Component | Base price amount | Applicable calculated amount | Difference |
|---|---|---|---|
| USD 10,000 foreign-currency element | ₹820,000 at ₹82 | ₹840,000 at ₹84 | +₹20,000 |
| Separately stipulated duty/tax component | ₹60,000 | ₹54,000 | −₹6,000 |
| Unchanged local component | ₹300,000 | ₹300,000 | Nil |
| Total | ₹1,180,000 | ₹1,194,000 | +₹14,000 |
The ₹14,000 is a reconciliation of the specified components before any other applicable controls, not a complete payment entitlement. The exchange increase is partly offset by the duty/tax reduction. Claiming the full ₹20,000 while ignoring the ₹6,000 reduction would overstate this limited adjustment by ₹6,000. Applying a second index increase to the same element without a supporting clause would risk double-counting; do not invent either an entitlement or a universal prohibition without reading the actual formula.
This separate contract does not inherit Cedar’s shares, advance, 2% trigger or 6% ceiling. A complete actual clause must specify its own interaction between price components and any controls. Keep the foreign-currency amount, applicable selling rate, documentary proof, tax evidence and unaffected elements visible.
6. Record the mode and terms of payment
Clause (k) requires the mode and payment terms for admissible variation to be included. A calculated adjustment is not automatically an immediately payable cash amount. The file should be able to identify the agreed claim documents, applicable calculation date, approval/verification requirements, payment method and timing, and treatment of earlier credits under the actual contract.
The selected clauses do not themselves prescribe one universal invoice format, certification workflow or bank-transfer date. Where those terms are missing or unclear, record the issue for proper resolution rather than fill it with an invented procedure. The workpapers in this lesson remain explanatory calculations, not payment orders.
7. Six graded practices with complete solutions
Practice A: exclude a paid portion
A different ₹1,000,000 contract has ₹250,000 paid at base indices, with no earlier variation due. The remaining portion attracts a properly established 6% weighted increase. Ignore thresholds/caps only for this stated raw calculation.
Solution. Unpaid base is ₹750,000; adjustment ₹45,000. Total price is ₹1,045,000 and remaining amount after the earlier payment ₹795,000. Applying 6% to the full base would overstate variation by ₹15,000.
Practice B: no later-index reward for supplier default
A supplied original-date adjustment is ₹30,000. Later indices during supplier-default delay would give ₹50,000, without an applicable amendment. What does the selected date restriction prevent?
Solution. It prevents the additional ₹20,000 claim based on indices beyond the original scheduled date for that default. The ₹30,000 still needs its ordinary calculation and contract checks; this is not a claim that every other payment condition is satisfied.
Practice C: an extension request is not the amendment
A contractor requests extra time for an alleged force-majeure event and immediately uses later indices. The file supplies no competent determination or specific contract amendment. Is clause (i)’s route established?
Solution. No. Establish the actual qualifying facts and specific authorised change to the scheduled date and relevant terms. Do not treat the contractor’s unilateral request as the required amendment.
Practice D: damages base and prior payment
An original contract has a properly varied price of ₹520,000, stipulated damages of 2% of that whole varied price, and ₹100,000 already paid. Calculate the limited remaining balance.
Solution. Damages are ₹10,400. Remaining amount = ₹520,000 − ₹10,400 − ₹100,000 = ₹409,600. The 2% is a supplied contract term, not a GFR-prescribed universal rate.
Practice E: exchange movement and a tax reduction
A separate clause fixes a USD 5,000 element. Its applicable selling rate moves from ₹80 to ₹81.50, while the separately evidenced duty/tax amount falls from ₹30,000 to ₹28,000. Other components are unchanged. Calculate the limited net adjustment.
Solution. Exchange increase is USD 5,000 × ₹1.50 = ₹7,500. The ₹2,000 duty/tax reduction leaves a ₹5,500 net increase. No current exchange or tax rate is asserted by these fictional values.
Practice F: price versus remaining cash
A workpaper correctly establishes total price ₹900,000 and records ₹200,000 already paid. It then describes ₹1,100,000 as the “remaining amount to be paid” by adding that payment. Repair it.
Solution. The total price remains ₹900,000. Credit the earlier payment to obtain ₹700,000 remaining before other applicable adjustments. Adding the payment overstates the remaining balance by ₹400,000 compared with the correct ₹700,000.
8. Explained objective questions
MCQ A. What is scenario A’s remaining amount before other deductions? (a) ₹2,464,000. (b) ₹1,680,000. (c) ₹1,664,000. (d) ₹2,064,000.
Answer: (c). The paid portion is frozen, giving ₹64,000 variation on the unpaid base, and the ₹400,000 payment is credited. Option (a) adds the payment again, (b) varies the full base, and (d) is the total price rather than the remaining amount.
MCQ B. Which scenario B treatment follows the supplied clause? (a) Use the original permissible dates and calculate the stated percentage damages on the properly varied price. (b) Use the latest indices automatically because delivery was eventually accepted. (c) Calculate damages only on the amount remaining after the advance, despite the supplied whole-price term. (d) A later invoice itself changes the scheduled delivery date.
Answer: (a). It preserves both the date restriction and damages base. Acceptance, a payment credit or an invoice does not establish the other alternatives.
9. Written-answer model and recap
Model answer. Rule 225(viii) requires payment-date and delay controls in addition to the index formula. Cedar’s ₹400,000 paid portion is frozen at the supplied unchanged base indices. Applying the original-date 4% weighted increase to the unpaid ₹1,600,000 gives ₹64,000, within the stated trigger and ceiling, so total price is ₹2,064,000 and the unpaid balance ₹1,664,000 before other deductions. Supplier-default delay does not permit the later indices. Under the stated late-acceptance damages term, 1% of the properly varied price is ₹20,640, leaving ₹1,643,360 after the earlier payment. A qualifying force-majeure or Government-default route needs the specific authorised amendment and relevant dates. Separately stated taxes and exchange elements require their own evidence and must not be double-counted. The contract must also state payment mode and terms; a workpaper does not itself authorise payment.
Summary. Trace the price portion, input date, cause of delay and actual clause before settling the arithmetic. Keep total price, admissible adjustment, damages and earlier payments as distinct lines.